Tag: Vantaa Light Rail Kuninkaala - Mellunmäki

The roundabout at Kyytitie and Porttisuontie will be converted into a signal-controlled intersection on 27 January 2026.

News

The roundabout intersection at Kyytitie and Porttisuontie will be converted into a signal-controlled junction during the night of 26–27 January 2026. The number of driving lanes will remain the same despite the change. However, as the work progresses, there may be some temporary changes to the lanes

Hakunila major region Tikkurila major region

Pelto-oja Road closed to vehicle traffic from 12 January 2026

News

Pelto-oja Road closed to vehicle traffic from 12 January 2026. The closure will last for two years.

Länsimäki Dog Park Closed 26 Jan–8 Feb 2026

News

Construction of the Vantaa tramway is progressing along Länsimäkivägen, and in the next phase the construction site will move to the area of the Länsimäki dog park. For this reason, the Länsimäki dog park will be completely closed from 26 January to 8 February 2026.

Hakunila major region

Vanha Porvoontie will be closed to car traffic between Kyytitie and Kokkokalliontie from 19 January to 6 February 2026

News

Vanha Porvoontie will have to be closed to car traffic between Kyytitie and Kokkokalliontie for the period 19 January–6 February 2026. During the closure, bus and car traffic will be directed to use Kyytitie and Kanervatie.

Tikkurila major region

Traffic Arrangements Will Change on Kyytitie at Porttipuisto in January

News

The Vantaa Light Rail construction sites will change traffic arrangements on Kyytitie from the Porttipuisto area towards Lahdenväylä. The roundabout at the intersection of Kyytitie and Porttisuontie will be removed and replaced with traffic lights. The pedestrian and cycling route along Kyytitie

Hakunila major region Tikkurila major region

Work causing significant noise will begin on Kyytitie in early 2026

News

On Kyytitie, work that cause significant noise will begin in early 2026. The work will take place in the area of the Heidehofintie roundabout and from the Porttisuontie roundabout towards the Lahdenväylä.

Hakunila major region Tikkurila major region

During construction works on Länsimäentie, a rock formation has been encountered that requires the start of a noisy work phase on 8 January 2026.

News

In connection with construction works carried out on Länsimäentie, next to Porvoonväylä, bedrock has been encountered. The works in the area are related to water supply infrastructure, which makes rock excavation necessary. Blasting works in the area will begin at the earliest on Thursday, 8 January

Hakunila major region

Construction of the Vantaa Light Rail on Länsimäentie during the Christmas–New Year holiday period, 29–31 December

News

Construction work on the Vantaa Light Rail along Länsimäentie in the area of the bridge crossing Porvoonväylä will continue during the holiday period 29–31 December. Preparatory work for the construction of the new bridge will be carried out in the area, which will require some traffic lanes to be

Hakunila major region

Construction work on the Vantaa Light Rail expands in December around the bridge crossing Porvoonväylä

News

Preparatory works for the Vantaa Light Rail began in November on Länsimäentie in the area surrounding the bridge crossing Porvoonväylä. After the City Council approved the updated project plan, the project has now moved into the construction phase on Länsimäentie.

Hakunila major region

Work Phase That May Cause Noise Begins on Länsimäentie South of Porvoo Motorway

Release

Work Phase That May Cause Noise Begins on Länsimäentie South of Porvoo Motorway

Hakunila major region