Work on the Vantaa Light Rail continues — tracks 3 and 4 will be out of use from 5 September to 17 October in the Tikkurila station area

News

Preparatory work on the Vantaa Light Rail will continue in the Tikkurila station area. Track 2 will be out of use from 5 September to 17 October. Noisy construction work will be carried out around the clock between September 19 and 8 October. Tikkurila station will operate as normal throughout this period.

Työmaa on ratapihalla.

During the interruption to rail traffic, construction work will be carried out at track 2. Some of the work will cause noise, and noisy work will also be occasionally carried out at night. Noisy nighttime construction work will be carried out between September 19 and 8 October, during which time the construction site will be active around the clock.

We will inform you if there are any changes to these planned times. We need to carry out noisy work at night because there is less traffic on the main railway at night, and our work must accommodate railway traffic.

Examples of work that will cause noise include the installation of sheet pile walls and bored pile driving.  During interruptions to rail traffic, temporary bridges will be put in place in the track and station platform area. The construction of the tunnel can continue under these bridges even after the interruptions to rail traffic. Piling wall structures will also be installed in the excavation during the interruption to rail traffic.

We will monitor the noise level, and we have built a noise barrier to reduce noise at the commuter traffic terminal, for example. We will carry out the work with as little noise as possible. We apologise for any inconvenience this may cause, and we thank you for your patience. 

If you wish, you can pick up earplugs from Tikkurila Library at Lummetie 4 during the library's opening hours. 


Changes in train traffic through Tikkurila station until December

The work will affect train traffic through Tikkurila station from June to December 2025.

There are also changes to the departure platforms of trains at Tikkurila station during this period. We recommend that you always check your train’s departure platform from the information boards at the station or VR’s and Fintraffic’s communication channels. You should also keep an eye on the signs posted in the platform area.

There will be service interruptions in commuter train traffic and replacement bus services at night from October 5 to 10.

More detailed information on train timetables is available on the HSL website, for example

https://www.hsl.fi/

Advance information on upcoming interruptions to rail traffic

If the work in the Tikkurila station area progresses according to plan, track 1 will be out of use from 27 October to 12 December, and noisy work will be carried out during the day and night from 1 November to 15 November. Any changes to the planned times will be announced in advance. 

According to the plan, the interruptions to rail traffic will end on 12 December. However, the construction of the tunnel will continue in the station area for several years. 

Tikkurila station operates as normal

Tikkurila station will operate as normal in spite of the preparatory work on the Vantaa Light Rail being carried out in the rail yard.